Sprint Backlog - No Active Members for this Sprint

Frequent Advisor

Sprint Backlog - No Active Members for this Sprint

I've seen this frequently but I don't know why. 

 

I am in Sprint Planning and I can't seem to move from Sprint to Sprint - it is greyed out.  And it also tells me "There are no active members for this sprint" - screen print is attached. 

 

What is the cause of this?  How to I stop if from happening? Is this a Defect?

 

After I move around in AGM for a bit, I go back and the members are there - did I do something to make it change?

 

Thanks in advance...Deb

 

6 REPLIES
Frequent Advisor

Re: Sprint Backlog - No Active Members for this Sprint

Hi Deb,

 

Please navigate to

configuration >  Release > Choose the right Release > Additional Setting 

Can you please check if the "Release Working Days:" are set?

 

Thanks

Ronen

 

Frequent Advisor

Re: Sprint Backlog - No Active Members for this Sprint

No, the Release Working Days are not set...so I assume they should be?

Highlighted
Frequent Advisor

Re: Sprint Backlog - No Active Members for this Sprint

But...even though I added the days, the problem still exists. And again, once I navigate in and out a few times, the members eventually show up.

Frequent Advisor

Re: Sprint Backlog - No Active Members for this Sprint

Hi DebKelchner,

 

Yes it should, please set the working days and check if it solve the probelm....

 

Thanks

Ronen

Advisor

Re: Sprint Backlog - No Active Members for this Sprint

I have the same problem.  The release days seem to being removed and going back in and 'ticking' them does not solve this problem.

Advisor

Re: Sprint Backlog - No Active Members for this Sprint

Cannot set the working days as after ti8cking the relevant days and clicking 'Save'   the update does not work despite the 'Item successfully saved' message.