Upgrade from ITG 6 -> PPM 9x

Established Member

Upgrade from ITG 6 -> PPM 9x

Hi Experts,


We are planning to upgrade our ITG 6 version to the latest PPM 9.21 version. Request you to help us with your expert comments on below questions.

  1. As far as we know, we cannot directly move to 9x version than going with a multi stage upgrade (6.0 -> 7.1 -> 7.5 -> 8.0 -> 9.1 ->9.21 )

Please let us know if there any other options than the above mentioned multilevel upgrade.

  1. We are planning to install a new ITG 6 version in a new box and clone it with the latest data and start the 6x to 7x upgrade. Any suggestions?

We are expecting your valuable comments on this topic




Honored Contributor

Re: Upgrade from ITG 6 -> PPM 9x

You are right... this is the correct approach. There is no other shortcut.