Quality Center Support and News
Showing results for 
Search instead for 
Do you mean 

Move from QC 9.2 to ALM 11

Occasional Visitor

Move from QC 9.2 to ALM 11

We are currently running QC 9.2.0.5132 with both the Server and DBServer on the same box and database MSSQL 2000 and would like to upgrade to ALM 11 MSSQL 2008.  Is there a best practices for doing these two moves, should we: 1 - upgrade the database, then upgrade the application, then update the projects or 2 - upgrade the application, then update the projects, then upgrade the database?

 

Regards,

Nate Carlson

1 REPLIES
Highlighted

Re: Move from QC 9.2 to ALM 11

Take a look at the attached Upgrade Guide - it walks through the different possibilities for upgrading.  You can go directly from 9.2 to version 11 and the guide describes upgrading other platform components as well and in what order you should do them.

 

Thanks!

 

Melinda