C7000 Encloure Power Down and Power On procedure

Ang had a customer question:

 

**************

 

Do you have any material of C7000 Encloure Power Down and Power On procedure ? The enclosure is running in client production environment.

 

 

*****************

 

Reply from Todor:

 

**************

 

Below you’ll find a document on powering down a C7000 with its blades properly:

http://bizsupport1.austin.hp.com/bizsupport/TechSupport/Document.jsp?objectID=c01577967

 

the same info is to be found in the C7000 maintenance and service guide as well (page 30):

http://h20000.www2.hp.com/bc/docs/support/SupportManual/c00714237/c00714237.pdf

 

And as far as the power on procedure is concerned – I don’t think that there are any critical precautions to be considered there (at least no such are documented).

Just reverse the ‘power down’ steps.

 

****************

 

Questions?

1 REPLY 1
Trygve Henriksen
Respected Contributor

Re: C7000 Encloure Power Down and Power On procedure

Only one point.

 

Set the c7000 to start the servers with a few seconds delay between them, and if they use any external storage, that it has time to start properly before the first server is started.