Can you sequence the power on order for blades in an enclosure

 
SOLVED
Go to solution
darren franklin
Occasional Advisor

Can you sequence the power on order for blades in an enclosure

Can you sequence the power on order for blades in an enclosure. I need to ensure that certain blades power on prior to others, any idea how this can be achieved if at all please.??
2 REPLIES
Blazhev_1
Honored Contributor
Solution

Re: Can you sequence the power on order for blades in an enclosure

Hi,

there is a feature, which helps you to delay the power on of a particular server.

Check

http://forums12.itrc.hp.com/service/forums/questionanswer.do?threadId=1197003

It is explained how this can be made. It is easier to use the ilo, but you decide...

Hope this helps.

Regards,
Pac
darren franklin
Occasional Advisor

Re: Can you sequence the power on order for blades in an enclosure

Pac
Thanks for this it may just do the trick