- Community Home
- >
- Servers and Operating Systems
- >
- HPE Synergy
- >
- HPE Synergy
- >
- Re: New Path 3PAR with Direct Attach FLAT my Siner...
Categories
Company
Local Language
Forums
Discussions
Forums
- Data Protection and Retention
- Entry Storage Systems
- Legacy
- Midrange and Enterprise Storage
- Storage Networking
- HPE Nimble Storage
Discussions
Discussions
Discussions
Forums
Forums
Discussions
Discussion Boards
Discussion Boards
Discussion Boards
Discussion Boards
- BladeSystem Infrastructure and Application Solutions
- Appliance Servers
- Alpha Servers
- BackOffice Products
- Internet Products
- HPE 9000 and HPE e3000 Servers
- Networking
- Netservers
- Secure OS Software for Linux
- Server Management (Insight Manager 7)
- Windows Server 2003
- Operating System - Tru64 Unix
- ProLiant Deployment and Provisioning
- Linux-Based Community / Regional
- Microsoft System Center Integration
Discussion Boards
Discussion Boards
Discussion Boards
Discussion Boards
Discussion Boards
Discussion Boards
Discussion Boards
Discussion Boards
Discussion Boards
Discussion Boards
Discussion Boards
Discussion Boards
Discussion Boards
Discussion Boards
Discussion Boards
Discussion Boards
Discussion Boards
Discussion Boards
Discussion Boards
Discussion Boards
Discussion Boards
Discussion Boards
Community
Resources
Forums
Blogs
- Subscribe to RSS Feed
- Mark Topic as New
- Mark Topic as Read
- Float this Topic for Current User
- Bookmark
- Subscribe
- Printer Friendly Page
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
тАО09-26-2019 03:11 AM
тАО09-26-2019 03:11 AM
New Path 3PAR with Direct Attach FLAT my Sinergy
Hello.
I have one 3PAR with two nodes connect to direct attach my VC of Sinergy
I have two news Hbas for my 3PAR and I will change de path connect to new hba and delete old.
I view the Interconect VC the WWN correct my new Paths, but the virtual volumes present in the profile server show the old Paths.
I reaply the profile (shutdown server) and work it with the new Path.
How I Can give the servers new path 3PAR without reaply profiles?
I can't shutdown all Sinergy Servers.
Thanks!
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
тАО09-28-2019 01:06 AM
тАО09-28-2019 01:06 AM
Re: New Path 3PAR with Direct Attach FLAT my Sinergy
Hi,
I have two news Hbas for my 3PAR and I will change de path connect to new hba and delete old. - Was it done from profile?How did you changed the path/added new connections to server online?
You may try a profile refresh,else you need to have downtime to re-apply profile.
[Any personal opinions expressed are mine, and not official statements on behalf of Hewlett Packard Enterprise]
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
тАО09-30-2019 12:32 AM
тАО09-30-2019 12:32 AM
Re: New Path 3PAR with Direct Attach FLAT my Sinergy
So is it impossible to apply new paths without loss of service?
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
тАО10-04-2019 05:06 AM
тАО10-04-2019 05:06 AM
Re: New Path 3PAR with Direct Attach FLAT my Sinergy
How did you changed the path/added new connections to server online?Was it done by editing profile?
[Any personal opinions expressed are mine, and not official statements on behalf of Hewlett Packard Enterprise]
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
тАО10-10-2019 09:27 AM
тАО10-10-2019 09:27 AM
Re: New Path 3PAR with Direct Attach FLAT my Sinergy
You might need to re-apply profile and thats the only option i could think off to update the new paths.
[Any personal opinions expressed are mine, and not official statements on behalf of Hewlett Packard Enterprise]
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
тАО10-22-2019 12:30 PM
тАО10-22-2019 12:30 PM
Re: New Path 3PAR with Direct Attach FLAT my Sinergy
I just tested modifying SAN paths online in OneView 4.10.03 and 4.20.02 and both of them let me modify the SAN connections without taking down the server. However, I was using switched fabric topology and not direct attach.
[Any personal opinions expressed are mine, and not official statements on behalf of Hewlett Packard Enterprise]
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
тАО12-04-2019 04:37 PM
тАО12-04-2019 04:37 PM
Re: New Path 3PAR with Direct Attach FLAT my Sinergy
I have buried in the back of my head a memory that if you do something as simple as rename the profile, it will trigger the OneView to audit the SAN Paths and update Zoning as needed.
But I can't find where I read that.
I work for HPE