- Community Home
- >
- Storage
- >
- Midrange and Enterprise Storage
- >
- StoreVirtual Storage
- >
- Re: Query: Need guidelines for Maintenance on a 2 ...
Categories
Company
Local Language
Forums
Discussions
Forums
- Data Protection and Retention
- Entry Storage Systems
- Legacy
- Midrange and Enterprise Storage
- Storage Networking
- HPE Nimble Storage
Discussions
Discussions
Discussions
Forums
Forums
Discussions
Discussion Boards
Discussion Boards
Discussion Boards
Discussion Boards
- BladeSystem Infrastructure and Application Solutions
- Appliance Servers
- Alpha Servers
- BackOffice Products
- Internet Products
- HPE 9000 and HPE e3000 Servers
- Networking
- Netservers
- Secure OS Software for Linux
- Server Management (Insight Manager 7)
- Windows Server 2003
- Operating System - Tru64 Unix
- ProLiant Deployment and Provisioning
- Linux-Based Community / Regional
- Microsoft System Center Integration
Discussion Boards
Discussion Boards
Discussion Boards
Discussion Boards
Discussion Boards
Discussion Boards
Discussion Boards
Discussion Boards
Discussion Boards
Discussion Boards
Discussion Boards
Discussion Boards
Discussion Boards
Discussion Boards
Discussion Boards
Discussion Boards
Discussion Boards
Discussion Boards
Discussion Boards
Discussion Boards
Discussion Boards
Discussion Boards
Community
Resources
Forums
Blogs
- Subscribe to RSS Feed
- Mark Topic as New
- Mark Topic as Read
- Float this Topic for Current User
- Bookmark
- Subscribe
- Printer Friendly Page
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
тАО05-05-2022 08:02 AM - last edited on тАО05-06-2022 08:01 AM by support_s
тАО05-05-2022 08:02 AM - last edited on тАО05-06-2022 08:01 AM by support_s
Hello!
I have a customer who needs to add more DIMMs in a two-node VSA 2014. They will do a tech-refresh after this summer, currently they are far from HA . Thus they need to add extra DIMMs. I will assist them to shutdown the nodes one by one. Am I correct with below order for the tasks ?
Nodenames: vs1, vs2
VSAnames: vsa1, vsa2
1. Shutdown all unnecessary VMs on vs1 except vsa1
2. vMotion all running VMs from vs1 to vs2
3. Power off vsa1 from CMC...wait time set to 5mins
4. Maint Mode and shutdown vs1
5. Add extra DIMMS in vs1
6. Power on vs1
7. Exit Maint mode on vs1
8. Start upp vsa1 from CMC and wait for resync
9. vMotion all VMs to vs1
Follow the same process to shutdown vs2
Br / Tony
Solved! Go to Solution.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
тАО05-05-2022 09:03 AM
тАО05-05-2022 09:03 AM
Query: Need guidelines for Maintenance on a 2 node StoreVirtual VSA 2014
System recommended content:
1. HPE StoreOnce VSA Deployment and Configuration Guide
Please click on "Thumbs Up/Kudo" icon to give a "Kudo".
Thank you for being a HPE valuable community member.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
тАО05-05-2022 11:20 AM - edited тАО05-05-2022 11:41 AM
тАО05-05-2022 11:20 AM - edited тАО05-05-2022 11:41 AM
Re: Query: Need guidelines for Maintenance on a 2 node StoreVirtual VSA 2014
I think I was spot on.
Found this thread.
https://community.hpe.com/t5/StoreVirtual-Storage/HP-StoreVirtual-VSA-2014-VMware-maintenance/td-p/6700967#M8973
I should mention vCenter is located outside of the Storevirtual environment.
The single FOM is on a physical server.
So I should be safe I believe... Am I right?
Br / Tony
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
тАО05-06-2022 07:58 AM - edited тАО05-06-2022 07:58 AM
тАО05-06-2022 07:58 AM - edited тАО05-06-2022 07:58 AM
SolutionDone without any issues following below task order
1. Shutdown all unnecessary VMs on vs1 except vsa1
2. vMotion all running VMs from vs1 to vs2
3. Power off vsa1 from CMC...wait time set to 5mins
4. Maint Mode and shutdown vs1
5. Add extra DIMMS in vs1
6. Power on vs1
7. Exit Maint mode on vs1
8. Start upp vsa1 from CMC and wait for resync
9. vMotion all VMs to vs1
Follow the same process to shutdown vs2
Br /Tony