請問EVA3000開關機的完整步驟

 
watermelonyu
教授

請問EVA3000開關機的完整步驟

請問EVA3000開關機的完整步驟
8則回覆 8
watermelonyu
教授

請問EVA3000開關機的完整步驟

應該是跟 EVA 5000 的一樣吧
watermelonyu
教授

請問EVA3000開關機的完整步驟

應該是跟 EVA 5000 的一樣吧
watermelonyu
教授

請問EVA3000開關機的完整步驟

請見附檔的第26頁
watermelonyu
教授

請問EVA3000開關機的完整步驟

請問附檔在那兒??
watermelonyu
教授

請問EVA3000開關機的完整步驟

pdf 檔無法 attach, 所以我把內容 post 出來

----

Below is from "CV EVA user guide.pdf"

----

To shut down the array:



1. Select the appropriate array in the Navigation pane.



The Initialized Storage System Properties window for the selected array appears.



2. Click Shut down.



The Shutdown Options window appears.



3. Under System Shutdown, click Power down. If a delayed shutdown is desired, enter a value in the

Shutdown delay box to set a time delay (in minutes) to preface system shutdown initiation.



The controllers complete an orderly shutdown and then power off. Then, the disk enclosures power off. Wait for the shutdown to complete.



4. Turn off the power switch on the rear of each controller.



5. Turn off the circuit breakers on both of the rack power distribution units (PDU).



6. If your management server is an SMA and you are not using it to manage other storage arrays, shut down the SMA. From the SMA user interface, click Settings > Maintenance > Shutdown.





To start the array:



1. Verify that each fabric switch to which the controllers are connected is powered up and fully booted. The LED power indicator on each switch should be on. If you must power up the SAN switches, wait for them to complete their power on boot process before proceeding. This may take several minutes.



2. If you shut down the SMA, power it on and wait for it to completely boot. Verify the SMA is running by logging into it using the web interface.





NOTE:



Before applying power to the rack, ensure that the power switch on each controller is off.





3. Power on the circuit breakers on both rack power distribution units (PDUs). Verify that all drive enclosures are operating properly. The status indicator and the power indicator should be on (green).



4. Wait three minutes and then verify that all disk drives are ready. The drive ready indicator and the drive online indicator should be on (green). If the storage system does not include back-end

Fib
watermelonyu
教授

請問EVA3000開關機的完整步驟

透過commandview EVA也可以進行開關機哦.



可參考網址PDF的38-40頁.



http://h200007.www2.hp.com/bc/docs/support/SupportManual/c00212236/c00212236.pdf
watermelonyu
教授

請問EVA3000開關機的完整步驟

在 SMA 執行 shutdown 之後, 最重要的是以下步驟...

------------

關掉 EVA rack 電源之前,務必先關掉 EVA 兩個 controller 的電源,否則開啟 EVA rack 電源時,controller 會被同時開啟, 因為 disk 尚未 ready, EVA 將會有問題。
watermelonyu
教授

請問EVA3000開關機的完整步驟

請參考下列網址:

http://www.hp.com.tw/ssn/unix/0510/unix051004.asp



Thanks

Mike Wu